Transmission Master Plan System of Sumatra Study

  • Timing: March to October 2017.
  • Financing: PT PLN.
  • CLIENT/Beneficiary: PT PLN
  • System Demand: 70GW System Capacity 85GW

The Indonesian energy utility

PT PLN (the Indonesian energy utility) contracted Mercados-Aries International to review and update the planning methodology, have first-hand experience implementing more complex methods of analysis and provide capacity building to the staff involved with the planning process of the company. The services included:

  • Participation of the Consultant in the preparation of the Master Plan of Sumatra.
  • Review and propose enhancements on the Master Planning methodology and suggest the way to introduce the best international practices.
  • Perform the detail electrical analysis of the master plan.
  • Design and provide formal training on planning and operation tools and methods.